Project Charter

Prompt:

I am a project manager working for a chain of ten specialty donut and coffee shops in metropolitan area. Looking to develop a business app to support the chain. Create an initial project charter for this project. Then provide the following attachments with the project charter: 1. List of key stakeholders with roles and responsibilities assigned 2. List of potential project risks with proposed responses 3. Milestone chart to support the proposed project schedule

ChatGPT said:

Here is your initial project charter for a business app supporting a chain of ten specialty donut and coffee shops, followed by the requested attachments.


📜 Project Charter: Donut & Coffee Chain Business App

Project Title:
“Brew & Glaze: Business App for Operations, Loyalty & Engagement”

Project Manager:
[Your Name], Project Manager, Brew & Glaze Donut & Coffee Chain

Project Sponsor:
Chief Operating Officer, Brew & Glaze

1. Purpose and Justification

To streamline business operations, enhance customer engagement, and improve internal communication by developing a mobile and web business app. The app will support:

  • Customer-facing features (ordering, rewards, location finder)
  • Internal use (inventory, sales tracking, shift scheduling)
  • Marketing (notifications, feedback, seasonal promotions)

2. Objectives

  • Increase customer loyalty and engagement by 20% within 6 months
  • Reduce order processing times by 25%
  • Provide real-time visibility into store operations and inventory
  • Integrate digital promotions and push notification campaigns

3. Scope

In Scope:

  • App for iOS and Android
  • Backend management dashboard
  • Loyalty & rewards program
  • Real-time analytics dashboard
  • Store locator and ordering capabilities

Out of Scope:

  • Delivery logistics beyond in-store pickup
  • Third-party payment gateway development (we’ll integrate existing ones)

4. Budget Estimate

$200,000 – $250,000

5. Timeline

Estimated duration: 6 months (Start: August 2025 | Go-live: February 2026)


👥 Attachment 1: Key Stakeholders

StakeholderRoleResponsibilities
Project Sponsor (COO)Executive SponsorApproves budget, resolves high-level issues
Project ManagerProject LeadManages scope, budget, schedule, team coordination
IT DirectorTechnical AdvisorOversees architecture, system integration
Marketing LeadCustomer Experience LeadDesigns loyalty/reward features, feedback, promotions
Store Managers (10 total)Operational AdvisorsProvide input on POS, scheduling, and inventory features
External Dev AgencyApp DevelopersBuilds and tests the app
HR ManagerInternal Admin FeaturesEnsures app supports staffing and scheduling features
Customers (focus group)User AdvocatesParticipate in testing and feature feedback

⚠️ Attachment 2: Project Risks and Responses

RiskLikelihoodImpactMitigation/Response
Delays in development timelineMediumHighUse Agile sprints with weekly check-ins and a buffer in the schedule
Budget overrunMediumHighTrack costs monthly, prioritize MVP features
Low adoption by staff or customersMediumMediumOffer training + customer onboarding incentives
Data security breachLowHighEnsure encryption, strong access controls, and third-party audits
Feature creep (scope expansion)HighMediumUse change control process, define MVP clearly
Integration issues with POS and inventory systemsMediumHighEarly technical feasibility assessments
App store approval delaysLowMediumPlan for early submissions and beta testing

🗓️ Attachment 3: Milestone Chart

MilestoneTarget Date
Project Kickoff & Requirements GatheringAugust 1, 2025
Wireframes and UX/UI ApprovalAugust 31, 2025
Backend Architecture FinalizedSeptember 15, 2025
MVP Development CompleteOctober 31, 2025
Internal QA Testing BeginsNovember 1, 2025
Focus Group/Beta Testing with 3 LocationsNovember 15, 2025
Feedback IncorporationDecember 5, 2025
Staff Training and Documentation CompleteDecember 20, 2025
Final QA and UAT ApprovalJanuary 10, 2026
App Store SubmissionJanuary 15, 2026
Full Deployment/Go-LiveFebruary 1, 2026